Below grade/ground installation tips

  1. Excavate hole to a depth to avoid frost penetrating under pier. (Typically 4’ to 6’.)
  2. Apply Sonotube form to TubeBase footing form.
  3. Cut off excess plastic at top of wedges to desired Sonotube form size.
  4. Attach Sonotube form to TubeBase footing form with a minimum of 4, 1” screws.
  5. Place TubeBase footing form at desired location. (On undisturbed soil or 4”-6” of compacted crushed stone or gravel.)
  6. Install footing rebar if required. (Rebar installation should be approved and designed by a qualified engineer and meet all building code requirements.)
  7. Level/plumb Sonotube form/TubeBase footing form prior to backfilling.
  8. Sonotube form and TubeBase footing form combined cannot exceed/extend 24” or more above grade/ground.
  9. Have inspected by building inspector as required by different municipalities.
  10. Backfill making sure Sonotube form remains level/ plumbed at desired location.
  11. Prior to pouring concrete into Sonotube form invert spare TubeBase on top of Sonotube form to act as a funnel for concrete pour.
  12. Pour concrete.
  13. Install anchor bolt to accept bracket as required.

Above grade/ground installation tips

For any TubeBase footing form project which requires the combined use of a Sonotube form and TubeBase footing form to exceed/extend 24” above ground/grade when pouring concrete, the Sonotube form MUST be braced to prevent movement of Sonotube form while the concrete is curing. (Conventional methods: Strapping or 2X materials w/stakes; wooden collar; frame with side braces)

 

 